2. Installation
Power Connections
Power Connections
WARNING: Do not apply any type power to this control panel until all connections have been
! made and verified.
AC Connections
Disconnect (open) the circuit breaker in the AC main breaker panel and tag it “Out of Service”.
Note: Refer to "Power-Up Procedure" on page 30 before closing AC breaker.
Primary power required for the PDRP-1001 and PDRP-1001A control panels is 110/120 VAC, 50/60 Hz,
1.2 amps and for the PDRP-1001E is 220/240 VAC, 50/60 Hz, 0.6 amps.
Overcurrent protection for this circuit must comply with Article 760 of the National Electrical Code (NEC)
and/or local codes. Use #14 AWG (2.00 mm2) or larger wire with 600V insulation rating.
A separately fused and protected power connection to the panel should be supplied to prevent voltage
fluctuation and interruption of power.
Ground
Neutral
Hot
TB5
J2
AMP
J9
J3
Figure 4 AC Power Connections
Battery (DC) Connections
WARNING: Battery contains sulfuric acid which can cause severe burns to the skin and eyes and
! can destroy fabrics. If contact is made with sulfuric acid, immediately flush the skin or eyes with
water for 15 minutes and seek immediate medical attention.
CAUTION: Do NOT connect the battery interconnect wire at this time. Make this connection AFTER
! initial system primary power connection.
Place batteries into bottom of cabinet as shown below. See "Appendix A: Secondary Power Calculations"
on page 37 for calculation of correct battery rating.
Note: Batteries are shipped separately and should be mounted only after the cabinet has been installed, the conduit
connected, and all wiring pulled, tested, and made ready to be terminated.
Continued on the next page...
16
PDRP-1001 Instruction Manual PN 50734:D0 04/06/01