English
Language : 

MSC8252 Datasheet, PDF (52/68 Pages) Freescale Semiconductor, Inc – orderDual-Core Digital Signal Processor
Hardware Design Considerations
3 Hardware Design Considerations
The following sections discuss areas to consider when the MSC8252 device is designed into a system.
3.1 Power Supply Ramp-Up Sequence
The following subsections describe the required device initialization sequence.
3.1.1 Clock, Reset, and Supply Coordination
Starting the device requires coordination between several inputs including: clock, reset, and power supplies. Follow this
guidelines when starting up an MSC8252 device:
• PORESET and TRST must be asserted externally for the duration of the supply ramp-up, using the VDDIO supply.
TRST deassertion does not have to be synchronized with PORESET deassertion. However, TRST must be deasserted
before normal operation begins to ensure correct functionality of the device.
• CLKIN should toggle at least 32 cycles before PORESET deassertion to guarantee correct device operation. The 32
cycles should only be counted from the time after VDDIO reaches its nominal value (see timing 1 in Figure 33).
• CLKIN should either be stable low during ramp-up of VDDIO supply (and start its swings after ramp-up) or should
swing within VDDIO range during VDDIO ramp-up, so its amplitude grows as VDDIO grows during ramp-up.
Figure 33 shows a sequence in which VDDIO ramps-up after VDD and CLKIN begins to toggle with the raise of VDDIO supply.
VDDIO = Nominal
VDD = Nominal
1
VDDIO Nominal
VDD Nominal
PORESET/TRST asserted
VDD applied
CLKIN starts toggling
VDDIO applied
Time
PORESET deasserted
Figure 33. Supply Ramp-Up Sequence with VDD Ramping Before VDDIO and CLKIN Starting With VDDIO
Note: For details on power-on reset flow and duration, see the Reset chapter in the MSC8252 Reference Manual.
MSC8252 Dual-Core Digital Signal Processor Data Sheet, Rev. 3
52
Freescale Semiconductor