408-4430 Datasheet, PDF (2/3 Pages) TE Connectivity Ltd – Read these instructions and understand them before using the seating tool and support anvil.
408-4430
3.2. Application Tooling
Power for the seating tool must be provided by an
application tool (with a ram) capable of supplying a
downward force of 89 N [20 lb] per contact.
Manual Electric Servo Presses (CMP 6T) 1585699-8
and (CMP 12T) 1585698-8, and Bench Top Electric
Servo Press (CBP 5T) 1585696-9 are available for this
seating tool. For information on the presses, visit the
press-fit assembly equipment website at 
http://tooling.te.com/pressfit.asp.
4. SEATING
1. Set the seating height to the dimension shown in
Figure 2 (machine shut height will equal the seating
height plus the combined thickness of the pc board
and pc board support fixture).
2. Position the support anvil, grooved side up, into
the pc board support fixture, and center it under the
ram of the application tooling. Position the pc board
with the receptacle over the support anvil.
3. Position the shield or receptacle (with integral
shield) onto the pc board so that the contacts are
properly aligned to the pc board and the support
anvil. See Figure 2.
4. Insert the contacts into the pc board until the
compliant lead section of the contacts are resting
securely on, but have not fully entered, the pc
board.
5. Position the seating tool onto the shield.
6. Center the seating tool and shield under the ram
of the application tooling; slowly lower the ram until
it just meets the seating tool. Verify the alignment of
the pc board support, pc board, connector, shield,
seating tool, and anvil.
CAUTION
!
Damage to the pc board, seating tool, shield, or
receptacle may occur if the seating height is
improperly set, if the pc board is not properly
positioned over the support anvil, or if the seating
tool is not properly seated on the shield before
cycling the ram.
7. Cycle the ram according to instructions for the
application tooling. Check the assembly for proper
seating using the requirements in Figure 2.
8. Remove the pc board with the seated shield or
receptacle (with integral shield), or re-position the
pc board and pc board support for seating additional
shields or receptacles (with integral shields).
5. MAINTENANCE AND INSPECTION
Inspect the seating tool and support anvil using 
Figure 3 immediately upon arrival at your facility to
ensure that they have not been damaged during
shipment. Thereafter, regular inspections should be
performed by quality control personnel. Remove dust,
moisture, and other contaminants with a clean, soft
brush, or lint-free cloth. Do NOT use objects that could
damage parts. When not in use, store them in a clean,
dry area.
Note: View After Seating
Seating Height
(Shield or Receptacle with
Integral Shield Seated)
26.7+0.25/-0.00 mm
[1.050+.010/-.000 in.]
Applicator Shut Height
(Ram Fully Down)
(See Section 4, Step 1)
Contacts in PC Board Holes
and Aligned with Grooves in
Support Anvil
Rev C
Figure 2
Note: Not to Scale
Applicator Ram (Fully Down) (Ref)
Seating Tool Centered Under Ram
and Bottomed on Shield or
Receptacle (with Integral Shield)
PC Board (Ref)
Support Anvil
PC Board Support Fixture (Ref)
2 of 3